Manufacturing and construction
The process for completing the design and construction of a building is often divided into stages. This can be helpful in establishing milestones for the submission of progress reports, the preparation of information for approval, client gateways, and for making payments.
However, there is a great deal of ambiguity between the naming of stages by different organisations and the definition of what individual stages actually include, and so it is important that appointment documents make it clear specifically what activities fall within which stage, and what level of detail is required.
‘Manufacturing and construction’ is a new stage introduced by the RIBA Plan of work 2020. This replaces ‘Construction’ in the 2013 edition and reflects the increasing prevalence of manufactured systems and components and volumetric construction.
The RIBA Plan of Work is published by the Royal Institute of British Architects (RIBA). Split into a number of key project stages, the RIBA Plan of Work provides a shared framework for design and construction that offers both a process map and a management tool.
The RIBA Plan of Work 2020 changed the structure of the stages as shown below:
Stage | 2013 edition | 2020 edition |
0 | Strategic definition. | Strategic definition. |
1 | Preparation and brief. | Preparation and briefing. |
2 | Concept design. | Concept design. |
3 | Developed design. | Spatial coordination. |
4 | Technical design. | Technical design. |
5 | Construction. | Manufacturing and construction. |
6 | Handover and close out. | Handover. |
7 | In use. | Use. |
The 2020 edition of the RIBA Plan of Work suggests that stage 5, manufacturing and construction: ‘…comprises the manufacturing and construction of the Building Systems in accordance with the Construction Programme agreed in the Building Contract. Increasingly, digital technologies are being used to rehearse different construction activities, allowing Stage 5 to be faster and safer. As the construction industry moves towards greater uptake of offsite manufacturing, greater emphasis is also placed on the logistics of getting materials and large-scale components to site on time, and on the management of supply chain partners.’
Stage 5 concludes by issuing a practical completion certificate which allows the completed development to be handed over to the client. The Plan for Use Strategy described by the RIBA requires that several tasks are undertaken to prepare for this, before and after practical completion.
[edit] Related articles on Designing Buildings Wiki
- BREEAM and RIBA stages.
- Comparison of BIM work stages.
- Governance for Railway Investment Projects (GRIP).
- NBS.
- OGC gateway review.
- Plan of work.
- Project lifecycle for major road projects.
- Record keeping.
- RIBA Plan of Work for Fire Safety.
- RIBA plan of work v project plans v OGC gateways.
- RIBA plan of work.
- RIBA plan of work 2020.
- RIBA.
Featured articles and news
Delivering for tenants; National Retrofit Hub
New report offers recommendations to strengthen energy efficiency standards to protect private renters.
Government consultations for the summer of 2025
A year of Labour, past and present consultations on the environment, the built environment, training and tax.
CMA competitiveness probe of major housing developers
100 million affordable housing contributions committed with further consultation published.
Homes England supports Greencore Homes
42 new build affordable sustainable homes in Oxfordshire.
Zero carbon social housing: unlocking brownfield potential
Seven ZEDpod strategies for brownfield housing success.
CIOB report; a blueprint for SDGs and the built environment
Pairing the Sustainable Development Goals with projects.
Types, tests, standards and fires relating to external cladding
Brief descriptions with an extensive list of fires for review.
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.